Project Details

Client: Supreme Steel
Location: Calgary, Alberta
Capex: $1.42 Billion CAD
Project duration: 2017-2021
Owner: The Government of Alberta
Design firm: KGL Constructors (JV Kiewit, Graham and Ledcor)
Architect: N/A
Engineer: COWI
Contractor: KGL Constructors (JV Kiewit, Graham and Ledcor)

Scope of Work

  • Modeling and shop detailing of approximately 95 tons of structural steel for Bridge BR-24A of the Regina Bypass project which included plate girders, cross frames and horizontal bracing

Project Stats

  • Consists of 31 kilometres of six- and eight-lane divided highway, 14 interchanges, 47 bridges, one road flyover, one railway crossing (flyover), one culvert set, one tunnel, and three river crossings over the Elbow River and Fish Creek

dashed-icon

Highlights & Challenges

  • The project was completed on an aggressive design and construction schedule. The design-build contract was awarded in December 2012 and the fast-paced design commenced in January 2013. The bridge opened for traffic in December 2015, 4 months ahead of schedule.